T-309

4-4

1. At every power up.
2. At the end of every defrost.
3. After every diagnostic check that does not fall out-

side of the limits as outlined above.

d. Probe Check
A defrost cycle probe check is accomplished by

energizing just the evaporator motors for eight minutes

at the end of the normal defrost. At the end of the eight

minute period the probes will be compared to a set of

predetermined limits. The defrost indicator will remain

on throughout this period.

Any probe(s) determined to be outside the limits will

cause the appropriate alarm code(s) to be displayed to

identify which probe(s) needs to be replaced. The P5

Pre-Trip test must be run to inactivate alarms.

4.9 SEQUENCE OF OPERATION

General operation sequences for cooling, heating and

defrost are provided in the following subparagraphs.

Schematic representation of controller action are

provided in

Figure 4-2 and Figure 4-3.

Refer to Section 3

for detailed descriptions of special events and timers

that are incorporated by the controller in specific modes

of operation.

SET POINT

PULL DOWN

RISING

TEMPERATURE

--0.5_C

(0.9_F)

--0.20_C

+.20_C

HEATING

HEATING

AIR CIRCULATION

+2.5_C

(4.5_F)

UNLOADED OPERATION

MODULATED

COOLING

UNLOADED

AIR CIRCULATION

SET POINT

+.20_C

HEATING

+2.5_C

(4.5_F)

FALLING

TEMPERATURE

MODULATED

COOLING

UNLOADED

--0.5_C

(0.9_F)

AIR CIRCULATION

NOTE: TEMPERATURES INDICATIONS ARE ABOVE OR BELOW SET POINT

START UNLOADED,

TRANSITION TO

ECONOMIZED

OPERATION

--0.20_C

Figure 4-2 Controller Operation -- Perishable Mode