Alpha Technologies XM2, XM2-HV, XM2-HP User Manual

Page 49

Advertising
background image

3.2

AC Input Voltage Reconfiguration, continued

3.2.2 Reconfiguration from 240Vac to 120Vac, continued

Fig. 3-8, SW2 Settings

5.

Remove the five front panel screws. Lift the transformer module front panel up
and away from the chassis. The front handle and output fuse remain in place.

6.

Reconfigure the PDB to 120Vac input, according to Table 3-2.
• Change Switch 2-4 (SW2-4) to OFF, Switch 2-5 (SW2-5) to OFF

• Change Switch 2-6 (SW2-6) to OFF, Jumper 1 (JP1) to Open (120) and

Jumper 2 (JP2) to Open (120).

Positions of SW2 (-4, -5, -6) are shown for clarity. Do not adjust the other switch positions
during this procedure.

NOTE:

7. Replace the front panel.

8. Install the power supply into the enclosure as outlined in Section 2.1, Installation

Procedure.

ON

4 5 6

120Vac

240Vac

ON

4 5 6

Legend

OFF ON

49

017-805-B0-010 Rev. K2

Advertising