Commissioning, Before switching on – Lenze E82EV 8200 vector 15kW-90kW User Manual

Page 167

Advertising
background image

Commissioning

Before switching on

7

l

167

EDK82EV903 DE/EN/FR 5.1

7

Commissioning

7.1

Before switching on

(

Stop!

Special commissioning procedure after long−term storage
If controllers are stored for more than two years, the insulation resistance of
the electrolyte may have changed.
Possible consequences:

ƒ

During initial switch−on, the DC−bus capacitors and hence the controller are
damaged.

Protective measures:

ƒ

Form the DC−bus capacitors prior to commissioning. Instructions can be
found on the Internet (www.Lenze.com).

)

Note!

ƒ

Do not change the switch−on sequence.

ƒ

In the event of a fault during commissioning please see the chapter
"Troubleshooting and fault elimination".

In order to avoid personal injuries or material damage, check the following before
connecting the mains voltage:

ƒ

The wiring for completeness, short circuit, and earth fault

ƒ

The "emergency stop" function of the system

ƒ

The motor circuit configuration (star/delta) must be adapted to the output voltage
of the controller.

ƒ

If no function module is used, the FIF cover has to be fitted (delivery status).

ƒ

If the internal voltage source X3/20, e.g. of the standard I/O is used, terminals X3/7
and X3/39 have to be bridged.