Commissioning

Initial switch−on

6

l

129

EDBMB9340 DE/EN/FR 12.0

6

Commissioning

6.1

Initial switch−on

(

Stop!

ƒ

Prior to initial switch−on check the completeness, polarity, short circuit and
earth fault of the drive system wiring.

ƒ

Keep to the switch−on sequence!

1. If 935x brake choppers are integrated into the drive system:

– Ensure the mains supply is switched−off.
– Use switches S1 and S2 to adapt the 935x brake chopper to the mains voltage (see

documentation for the brake chopper).

2. Switch on the mains.

– The drive system will be ready for operation after approx. 0.5 s.

3. Control the readiness for operation via both LEDs at the front of the regenerative

power supply module:

Status

Description

green

red

on

off

l

The regenerative power supply module is connected to the mains voltage and is ready for
operation.

l

No faults.

off

on

Active fault

off

off

l

Mains voltage is switched off

l

Mains phase L2 or L3 failed

4. Adapt all controllers which are connected to the drive system to the mains voltage

(under C0173).