Before switching on

)

Note!

ƒ

Do not change the switch−on sequence.

ƒ

In the event of a fault during commissioning please see the chapter
"Troubleshooting and fault elimination".

In order to avoid personal injuries or material damage, check the following before
connecting the mains voltage:

ƒ

The wiring for completeness, short circuit, and earth fault

ƒ

The "emergency stop" function of the system

ƒ

The motor circuit configuration (star/delta) must be adapted to the output voltage
of the controller.

ƒ

If no function module is used, the FIF cover has to be fitted (delivery status).

ƒ

If the internal voltage source X3/20, e.g. of the standard I/O is used, terminals X3/7
and X3/39 have to be bridged.