Commissioning
Before switching on
6
l
98
EDK82MV752 DE/EN/FR 7.1
6
Commissioning
6.1
Before switching on
)
Note!
ƒ
Do not change the switch−on sequence.
ƒ
In the event of a fault during commissioning please see the chapter
"Troubleshooting and fault elimination".
In order to avoid personal injuries or material damage, check the following before
connecting the mains voltage:
ƒ
The wiring for completeness, short circuit, and earth fault
ƒ
The "emergency stop" function of the system
ƒ
The motor circuit configuration (star/delta) must be adapted to the output voltage
of the controller.
ƒ
If no function module is used, the FIF cover has to be fitted (delivery status).
ƒ
If the internal voltage source X3/20, e.g. of the standard I/O is used, terminals X3/7
and X3/39 have to be bridged.