Power connections, Bulletin 1562e – Rockwell Automation 1560E SMC Flex Smart Motor Controller User Manual

Page 53

Advertising
background image

Installation

2-5

Power Connections

The controller requires a three-phase supply and an equipment grounding
conductor to earth ground. A neutral conductor of the three-phase supply
is not necessary and is usually not routed to the controller. Three-phase
wiring will connect the controller to the motor.

Bulletin 1562E

The Bulletin 1562E unit is available in two main configurations:

1. A modified two-high cabinet (180/360A, 2400 to 4160 V)

2. A combination of a one-high full voltage non-reversing (FVNR)

cabinet and a 1560E unit (600A, 2400 to 4160 V, and 180/360/600A,
5500 to 6900 V)

To make power connections for a two-high cabinet, refer to Figures 2.1 to
2.3, and Publication 1500-UM055B-EN-P (Chapter 2).

To make power connections for a one-high FVNR cabinet and a 1560E
unit, proceed as follows:

• Make line connections within the one-high cabinet

• Make load connections at the 1560E CT terminals (refer to Figure 2.5 or

2.6)