Chapter 3 - commissioning procedure, Preliminary set-up, Commissioning procedure – Rockwell Automation 1560E SMC Flex Smart Motor Controller User Manual
Page 69: Chapter
Advertising
Commissioning Procedure
Preliminary Set-Up
A. Ensure the work area is clean and tidy. Pathways to main disconnect
and emergency stop push-button must be clear and unobstructed.
B. The following test equipment is to be prepared for use:
• Test power supply, supplied with each controller
• Multimeters
• Hi-Pot Tester (recommended) or Megger
• Oscilloscope with memory (optional)
C. Complete drawing package and parts list.
D. Specification of project.
Chapter
3
1560E-UM050B-EN-P - June 2013