Figure 2-3. tightening sequence – Comtech EF Data CST-5000 User Manual
Page 48
Advertising
![background image](/files/778811/content/doc048.png)
Single Thread System Installation
CST-5000 C-Band Satellite Terminal
2–20
Rev. 9
Figure 2-2. Mounting LNA to Antenna
5. Position the LNA in place on the antenna, and install the 1/4-20 x 1 inch (25 mm)
bolts, washers, and nuts (refer to Figure 2-2). Do not tighten at this time.
CAUTION
Install the hardware exactly as shown. Failure to do so may cause
damage to the LNA and/or waveguide.
6. After all the bolts, washers, and nuts have been installed, tighten them according
to the illustrated sequence shown in Figure 2-3.
1
2
3
4
5
6
7
8
9
10
Figure 2-3. Tightening Sequence