Single Thread System Installation

CST-5000 C-Band Satellite Terminal

2–20

Rev. 9

Figure 2-2. Mounting LNA to Antenna


5. Position the LNA in place on the antenna, and install the 1/4-20 x 1 inch (25 mm)

bolts, washers, and nuts (refer to Figure 2-2). Do not tighten at this time.

CAUTION

Install the hardware exactly as shown. Failure to do so may cause
damage to the LNA and/or waveguide.


6. After all the bolts, washers, and nuts have been installed, tighten them according

to the illustrated sequence shown in Figure 2-3.

1

2

3

4

5

6

7

8

9

10

Figure 2-3. Tightening Sequence