MAINTENANCE AND INSPECTION

So that the

inverter may give extended pe-

riods of trouble-free operation and to prevent poten-

tial problems from

the following items should

be periodically inspected.

WARNING BURN AND SHOCK HAZARD:

Do not conduct any Inspectlons until after discon-
necting the power supply and after the “CHARGE”
light on the inverter has gone out.

CAUTION:

When removina or

wires,

handle them

the connector onlv and not bv the

wire itself. Be careful not to mix wires when recon-

necting them.

MEGGER TEST

CAUTION:

Short all terminals as shown in Fiaure

7-1 and meqqer them all at one time. Do not meqqer
each terminal

3. Use a multi-meter set on a high resistance range

to conduct a continuity test on the control circuits
and not a megger or a buzzer.

PERIODIC PARTS REPLACEMENT

The life of the inverter will vary according to the

installation environment and the amount of running

time. However, if continuous operation is within the

allowable limits, the life of the DC Link capacitor is ap-
proximately five years and the life of the cooling fan is
approximately three years. It is recommended that

these parts be replaced before failure occurs.

INSPECTION ITEMS

Refer to the Inspection Items Chart in this section

for inspection points and corrective action.

NOTE: Perform

test

if

necessary.

1. Disconnect all inverter terminals and never apply

test voltage to the inverter when conducting an

external circuit megger test.

2. Perform the test only on the main circuit as shown

in Figure 7-l when conducting a megger test on

the inverter itself.

-- Do not conduct a megger test on the control

circuits.

CONTROL CIRCUIT

TB5

TERMINAL BOARD

MAIN CIRCUIT TERMINAL BOARD

L2 L3 u v w

N

P

MEGGER

Figure 7-1. MAIN CIRCUIT MEGGER TEST CONNECTIONS