3) Load cables for the power cell should be routed before control cables.

Pull the cables into the cabinet through the appropriate opening (see

Figures 3.12 and 3.13).

4) Remove current transformer barriers.

5) Connect the cables to the current transformers and tighten the

connections to 48 ft.lb (65 N.m).

6) Connect cable shields (if present) to the ground lug.

7) Reinstall the current transformer barrier and reassemble the cabinet.


Figure 3.12 – Load Cable Conduit Openings, Arc Resistant Cabinet

(Top Exit cable configuration shown, with plenum)