4-6

Common Installation

1512A-UM102B-EN-P – June 2013



Start-up Procedure

Contactor Inspection

See Chapter 2 in

Medium Voltage Contactor 800A, Publication 1502-

UM051_-EN-P for information on pre-energization inspection, vacuum

bottle integrity test and insulation resistance test.

Preliminary Checks

Verify the following:

• Contactor current and voltage ratings are correct for the attached

load;

• Control voltage is correct;

• Settings for protective relays;

• Heater elements (if provided) in overload relay are secure and

undamaged;

• Equipment grounding;

• External power and control connections match electrical diagrams;

All hardware is correctly reinstalled and torqued to specifications (see

page 1-3);

All barriers are replaced to correct positions;

All fuses are correct class, type and rating;

Mechanical interlocks and isolation switch function properly;

Ensure that any microprocessor-based protection relay is
programmed;

Interior of cabinet is free from dirt, loose bolts, tools or metal chips.
Vacuum clean if necessary;

All tools are accounted for. If you cannot locate a tool, do not
energize the unit until it is found.

Testing Contactor Operation

1) Connect the appropriate external power supply (120 or 230 V AC)

to the test receptacle in the control panel. Turn the selector switch to

the TEST position.