Burner Control/Flame Safety

Master/Slave Arrangement

Revision 7

HercuLine™ 2000 Series Actuator - Installation, Operation and Maintenance Manual

27

7/08

Basic Flow Control

When the process variable signal is below set point, the controller increases current (4 to 20mA) to the
actuator input and opens the valve. Controller set point governs valve position to obtain desired flow
rate.

PV

SP

4 to 20 mA

Controller

Positioner & Actuator

Linkage

Position

mA

Valve

Orifice Plate

FIC

MP

FT

Figure 16 Flow Diagram

Hot

Actuator

Neutral

Ground

120/240

VAC

250 Ohms
1 to 5 VDC

+

-

Current Output Controller

4 to 20 mA

Figure 17 Interconnection Diagram

Proportional Flow using Multiple Actuators

Refer to flow diagram in Figure 18 and interconnection diagrams in Figure 19. The controller governs
flow rate in one burner. Only that flow is measured. Since #2 and #3 motor positions receive the same
signal as #1 motor positioned, valves #2 and #3 will deliver the same amount of fuel. This is true when
the span and zero adjustment are all set the same as in curve 2 of the graph. Other relationships between
units exist if the span adjustment (3) for ratio or if the zero adjustment is changed (1) for bias.

Jumper W2