Important – Manitowoc Ice FLAKE/CHIPLET QF0400 User Manual

Page 139

Advertising
background image

Section 7

Refrigeration System

Part No. 80-1214-3

7-17

Self-Contained Model Charging Procedures

1. Be sure the toggle switch is in the OFF position.

Charging Connections

2. Close the vacuum pump valve, the low side service

valve, and the low side manifold gauge valve.

3. Open the high side manifold gauge valve, and

backseat the high side access valve.

4. Open the charging cylinder and add the proper

refrigerant charge (shown on nameplate) through
the discharge access valve.

5. Let the system “settle” for 2 to 3 minutes.

6. Place the toggle switch in the ICE position.

7. Close the high side on the manifold gauge set. Add

any remaining vapor charge through the suction
access valve (if necessary).

NOTE: Manifold gauges must be removed properly to
ensure that no refrigerant contamination or loss occurs.

8. Make sure that all of the vapor in the charging hoses

is drawn into the ice machine before disconnecting
the charging hoses.

A. Run the ice machine in freeze cycle.

B. Remove the quick disconnect fitting from the

high side access valve at the ice machine.

C. Open the low side service valve at the ice

machine.

D. Open the high and low side valves on the

manifold gauge set. Any refrigerant in the lines
will be pulled into the low side of the system.

E. Allow the pressures to equalize while the ice

machine is in the freeze cycle.

F. Remove the quick disconnect fitting from the low

side access valve at the ice machine and install
both access valve caps.

Important

The charge is critical on all Manitowoc ice
machines. Use a scale or a charging cylinder to
ensure the proper charge is installed.

SV3055

FRONTSEAT

BACKSEAT

OPEN

CLOSED

MANIFOLD SET

LOW SIDE

ACCESS

VALVE

HIGH SIDE

ACCESS

VALVE

SCALE

CLOSED

VACUUM

PUMP/

RECOVERY

UNIT

Revised 8/2003

Advertising