Installation Instructions

Section 2

2-16

Part No. 80-1214-3

Verify O-ring in schrader valve caps are intact and
reinstall on shut off valves to prevent refrigerant leakage.
Replace shut off valve access caps and torque to the
following specifications.

Torque Value’s

Replace cap on receiver service valve and tighten.

Open Receiver Service Valve

There is a liquid line solenoid valve at the outlet of the
receiver; refrigerant will not flow to the condensing unit
until the ice machine head section is started. Connect
power to both the ice machine head section and the
Remote condensing unit. Place the ICE/OFF/CLEAN
toggle switch into the ICE position, this will allow
refrigerant to enter the line set and condensing unit.

Step 7 Leak Check The Refrigeration System

Leak check the new line set connections at the ice
machine head section, condensing unit and S trap as
well as all factory joints throughout the entire system.
Disconnect power to the remote condensing unit. Place
the ICE/OFF/CLEAN toggle switch into the ICE position.
This allows the low side and high side pressures to
equalize. Place the ICE/OFF/CLEAN toggle switch in the
OFF position. Connect power to the remote condensing
unit and allow system to pump down.

Step 8 Insulation Requirements

To prevent condensation the entire suction line including
the shut-off valve must be insulated. All insulation must
be airtight and sealed at both ends.

The following insulation requirements prevent
condensation at 90°F (32.2°C) ambient 70% Relative
Humidity. If higher humidity is expected, increase
insulation thickness.

The entire line set, including the suction service valve
located on the back of the ice machine requires:

Stem

18-20 ft. lbs.

Caps

12-15 ft. lbs.

Schrader Core

1.5-3 in. lbs.

Important

All refrigeration valve caps must be reinstalled to
prevent future refrigeration leaks.

TURN

COUNTERCLOCKWISE

SV1756

RECEIVER SERVICE VALVE CAP

(TURN COUNTERCLOCKWISE

TO REMOVE)

Suction Line

Liquid Line

Min. Insulation

Thickness

3/4 inch

(19.1 mm)

1/2 inch

(12.7 mm)

1/2”(13mm)

Suction Line

1/4” (7mm)
Liquid Line

Important

To prevent condensation the entire suction line
including the shut off valve must be insulated. All
insulation must be airtight and sealed at both ends.
The minimum requirements are for conditions at or
below 70% humidity and 90°F (32.2°C) ambient.
When higher humidity will be experienced, insulation
wall thickness will need to be increased.