Wiring requirements – Powerware 5075 kVA User Manual

Page 20

Advertising
background image

12

Powerware BPIII Harsh Environment UPS 50--75 kV Installation and Operation

164291261 Rev. F 111503

FRONT

SIDE

FOAM

SUPPORT

SUPPORT

1

2

1

2

2

2

JACKING

BOLT

FLOOR

PROTECTOR

1

2

DOOR

CUSHION

Figure 3. Removing Front and Rear Supports

WARNING:

Cabinet may fall. Do not loosen hardware attaching the side or front supports

to cabinet base. Also, do not loosen supports from each other. The cabinet

must be lowered using jacking bolts before supports can be removed.

6.

Carefully and evenly lower the cabinet by turning each jacking bolt

consecutively two full turns (maximum) until the supports contact the floor, and

the cabinet is no longer supported by the jacking bolts.

7.

After the cabinet is resting on the floor, remove the jacking bolts and discard or

recycle them in a responsible manner.

8.

Remove the hardware labeled “2” in Figure 3, holding the front, rear and side

supports to the cabinet base. Discard or recycle the hardware and support

brackets in a responsible manner.

9.

Replace the door that was removed in step 1. The cabinet is now ready to be

rolled to its final location.

10.

Repeat steps 1 through 9 for the Environmental cabinet.

Wiring Requirements

For external wiring requirements, including the minimum AWG size of external

wiring, see Tables A and E of Appendix A. The power wiring for this equipment is

rated at 90˚C.