Powerware BPIII Harsh Environment UPS 50--75 kVA Installation and Operatio

n

164201261 Rev. F 111503

Installation Checklist

-

All packing materials and restraints have been removed from each cabinet.

-

Each cabinet in the UPS system is placed in its installed location.

-

All cabinets are bolted together.

-

A ground bond is installed between all cabinets that are bolted together.

-

All switchboards, conduits, and cables are properly routed to the UPS.

-

Power cables are terminated on AC Input terminals (UPS Cabinet) (E1---E3).

-

Power cables are terminated on Bypass Transformer input terminals (UPS Cabinet)

(E13---E15).

-

Power cables are terminated on AC Output terminals (UPS Cabinet) (E9---E12).

-

Power cables are terminated on DC Input terminals (UPS Cabinet) (E4---E5).

-

Power cables are terminated on bypass terminals (E19---E21).

-

Power cables are terminated on the CB1 input breaker (E33---E35 ).

-

Power cables are terminated on output terminals (E25---E27).

-

A ground conductor is properly installed.

-

If N is used, no other N---G bonds exist downstream from the UPS.

-

Battery cables and harness are terminated on the CB2 battery breaker E31 and E32.

-

The area around the installed UPS system is clean and dust-free. (It is recommended

that the UPS be installed on a sealed concrete pad on a sealed concrete floor.)

-

Adequate workspace exists around the UPS and other cabinets.

-

Adequate lighting is provided around all UPS equipment.

-

A 120V service outlet is located within 25 feet of the UPS equipment.