Operation – Powerware 5075 kVA User Manual

Page 74

Advertising
background image

66

Powerware BPIII Harsh Environment UPS 50--75 kV Installation and Operation

164291261 Rev. F 111503

Operation

The following sections describe how to operate the controls to start, stop, or

change the operating mode of the UPS.

To Place the UPS in Normal Mode:

1.

Close BIB circuit breaker.

2.

Close

CB1 circuit breaker.

3.

Turn the

BATTERY switch to NORMAL.

4.

Turn the

MODE switch to NORMAL.

5.

Ensure the Emergency Power Off

PUSH TO RESET pushbutton is pressed in.

6.

Turn the

START switch to the right momentarily.

After the rectifier reaches 540 VDC, the DC to DC converter begins to turn on.

After the converter reaches full voltage, the

OK To Close CB2 notice is

displayed on the Monitor Panel LCD screen.

7.

When the

OK To Close CB2 notice is displayed on the Monitor Panel LCD

screen, close circuit breaker

CB2.

The inverter begins to turn on. When the inverter reaches full voltage, it turns

on and supplies power to the critical load.

If a bypass source is available when you turn the

START switch on, the critical

load is immediately supplied by the bypass source in Bypass mode until the

inverter turns on and the UPS transfers to Normal mode. The status indicators

on the Monitor Panel indicate when the UPS is in Bypass mode and Normal

mode.

To Shut Down the UPS from Normal Mode:

1.

Turn the

MODE switch to BYPASS.

The UPS switches to Bypass mode. If the bypass source is not available, the

power processor remains on and an alarm sounds.

2.

When the transfer is complete (the LCD screen reads On Bypass), move the

CB2 breaker switch to OFF. Then move the CB1 breaker switch to OFF.
The bypass source supplies the critical load and the power processor

de-energizes. The Bypass mode indicator illuminates on the Monitor Panel.