Technical Product Manual - DCT1900

Installation Instructions, Modular Cabinet – CLU/SLU to Base Station Cabling

Install-DCT1900/R8/mw

21-3

© 2000-2005

Fig. 21–2 CLU/MDF Cable Connections on the CLU or SLU

Base Station Power
The following installation steps are necessary when the Base Stations are powered via the
Modular Cabinet. Refer to Chapter 19 on how to supply Base Station power to the MCCB.
1.

Connect connectors PW1 on the MCCB to the Base Station power connectors on the furthest
left CLU or SLU using the CLU/MCCB Power cable (see Fig. 21–2).

2.

Connect PW2 – PW7 to the power connections of the other CLU or SLUs starting at the next
CLU or SLU.

Cabling from the MDF to the Base Station
Refer to Section 4, Chapter 4, Base Station Powering for cable type information. Figure 21-3
shows the pinout of the 66 blocks that the cable set NTM/TSRNB 101 29 terminates on. NOTICE
that only 3 pairs are brought out for each base station. These are SC0, SC1 and EPP0/1.

You must hook up the first 2 pair, SC0 and SC1, for each base station. The third pair, EPP0/1, is
only used when additional power is required due to cabling distances. (Refer to Section 4,
Chapter 4, Base Station Powering).

If a fourth pair (white/brown pair) is required then it may be punched down on top of the existing
EPP0/1, pair (white/green pair).

CLC1

CLC2

CLC3

CLC4

CLC5

CLC6

CLC7

CLC8

To cable TSRNB 101 29/2 or
TSRNB 101 46/2

To cable TSRNB 101 29/1 or
TSRNB 101 46/1

Base
Station
Power

To cable TSRNB 101 33