SECTION 6 - GENERAL SPECIFICATIONS AND OPERATOR MAINTENANCE

3128790

– JLG Lift –

6-17

Wire Cable Adjustment

To check for correct wire cable tension position machine on a
firm, level, and uniform surface.

1. Remove the cover on the third boom section

2. Loosen the register counter-nuts allowing for access to

the wire cable adjustment nuts

3. Position both boom extensions until approximately 12-15

inches of the inner booms are showing

4. Tighten nuts on the retract cables to a torque of 10Nm

(7.4ftlbs)

5. Fully extend both boom extensions. Retract the boom

extension sections between 12-15 inches.

6. Torque the bolts on the extend cables until the threads

extend 2-1/2 ±0.11 inches (65mm ±3mm) from the
boom section. Do not twist cable while tightening.

7. Cycle the boom extensions five (5) times and verify the

wire cables are at a torque of 10Nm (7.4ft-lbs)

8. Verify during the cycle testing that no rubbing occurs

from the wire rope cables

9. Upon verification tighten the counter-nuts and reattach

any removed covers

2-1/2 ±0.11 in.

65 ±3 mm