Calibrating and Bump Testing the PPM Com-

instrument is not in a fresh air environment, connect a gas bag with
zero air to the rigid tube on the probe using the 6 inch humidifier
tube and open the clamp allowing the instrument to draw zero air
for 2 minutes.

6. Hold down the AIR▲ button. The unit will prompt you to continue

holding the AIR▲ button.

7. When the unit prompts you to release the AIR▲ button, release it.

The instrument will perform a fresh air adjustment on the ppm
sensor and return you to the AIR CAL menu item. If a gas bag with
zero air was used, disconnect the humidifier from the probe.

NOTE:

Grasp the humidifier tube assembly by the clear tubing at the
end, not the humidifier tube itself.

Performing a Dry Fresh Air Adjustment

This section describes how to perform a fresh air adjustment on the
PPM combustible gas sensor using the DRY setting. Use the DRY
setting with a gas bag filled with zero air for a biannual calibration.

NOTE:

It is recommended that you perform a fresh air adjust on the
ppm sensor using a gas bag filled with zero air and the DRY
setting followed by a fresh air adjustment using the WET
setting once every 6 months to maintain the accuracy of the
ppm combustible gas reading. See “Performing a Wet Fresh
Air Adjustment” on page 100 for instructions to perform a
WET fresh air adjustment.