What is the SoftLogix System?

Determining Programs

Each program contains program tags, a main executable routine, other routines,
and an optional fault routine. Each task can schedule as many as 100 programs
(including equipment phases).

The scheduled programs within a task execute to completion from first to last.
Programs that are not attached to any task appear as unscheduled programs. You
must specify (schedule) a program within a task before the controller can scan
the program.

Table 2 - Task Execution Order for Application with Periodic Tasks and Continuous Task

Task

Priority Level

Task Type

Actual Execution Time

Worst Case
Execution Time

1

1

20 ms periodic task

2 ms

2 ms

2

2

10 ms periodic task

4 ms

6 ms

N/A

None (lowest)

Continuous task

25 ms

35 ms

N/A

None

Dwell time

10 ms

14 ms

Task 1

Task 2

Continuous

Task

Dwell

Time

Task

Description

A

The highest priority task interrupts all lower priority tasks.

B

A lower priority task can be interrupted multiple times by a higher priority task.

C

The continuous task runs at the lowest priority and is interrupted by all other tasks.

D

The dwell time starts when the continuous task completes. The dwell time does not affect periodic tasks.
Periodic tasks execute as scheduled, regardless of the dwell time.

E

The continuous tasks restart, when the dwell time completes, unless a higher priority task is running.