3.0 OPERATING PROCEDURES

3.1

EZCT S2A Cable Connections

Always connect the EZCT S2A to the substation ground before connecting any test cables. The X
cable connections are required to run the current transformer excitation test. The H and X cable
connections are required to run the transformer turns-ratio test. A typical excitation and ratio
test connection is shown in Figure 2. Transformer bushing CT connections for Delta and Y
transformers are shown in Figure 3 and Figure 4, respectively.

Figure 2. Typical EZCT S2A Excitation and Ratio Test Cable Connection