Preventative Maintenance Schedule

E-5

7000 “A” Frame

7000A-UM151D-EN-P – March 2013



Additional Tasks During Preventive Maintenance

Investigation of customer’s concerns relating to drive performance

Relate any problems found during above procedures to

customer issues.

Informal instruction on drive operation and maintenance for plant

maintenance personnel

Reminder of safety practices and interlocks on MV equipment,

and on specific operating concerns

Reminder of the need to properly identify operating conditions

Recommendation for critical spare parts which should be stocked

in-plant to reduce production downtime

Gather information on all spare parts on site, and compare that

with factory-recommended critical spares to evaluate whether
levels are sufficient.

Contact MV Spare Parts group for more information.

Vacuum Bottle Integrity Testing using a Vacuum Checker or AC

Hipot

Refer to Publication 1502-UM050_-EN-P for a detailed

description of all contactor maintenance.

Final Reporting

A complete, detailed report on all steps in the Preventive

Maintenance procedures should be recorded to identify changes.

A completed copy of this checklist should be included.
A detailed description of ALL ADJUSTMENTS AND

MEASUREMENTS that were taken during the process should
be included in an addendum (Interlock Adjustments, Loose
Connections, Voltage Readings, Megger Results, Parameters,
etc.)

THIS INFORMATION SHOULD BE COMMUNICATED TO MV

PRODUCT SUPPORT SO THAT FUTURE SUPPORT
ACTIVITIES WILL HAVE THE LATEST SITE INFORMATION
AVAILABLE.

This can be faxed to (519) 740-4756, or
E-mailed to:

[email protected]