Communication

3.3 S7 connections

CPU 31xC and CPU 31x, Technical data
Manual, Edition 08/2004, A5E00105475-05

3-27

Connection points

An S7 connection between modules with communication capability is established between

connection points. The S7 connection always has two connection points: The active and

passive connection points:

The active connection point is assigned to the module that establishes the S7 connection.

The passive connection point is assigned to the module that accepts the S7 connection.

Any module that is capable of communication can thus act as an S7 connection point. At the

connection point, the established communication link always uses one S7 connection of the

module concerned.

Transition point

If you use the routing functionality, the S7 connection between two modules capable of

communication is established across a number of subnets. These subnets are

interconnected via a network transition. The module that implements this network transition

is known as a router. The router is thus the point through which an S7 connection passes.
Any CPU with a DP or PN interface can be the router for an S7 connection. You can

establish a certain maximum number of routing connections. This does not limit the data

volume of the S7 connections.

See also

Connection resources for routing (Page 3-31)

3.3.2

Assignment of S7 connections

There are several ways to allocate S7 connections on a communication-capable module:

Reservation during configuration

Allocating connections via programming

Allocating connections during commissioning, testing and diagnostics routines

Allocating connection resources to OCMS services

Reservation during configuration

One connection resource each is automatically reserved on the CPU for PG and OP

communication. Whenever you need more connection resources (for example, when

connecting several OPs), configure this increase in the CPU properties dialog box in

STEP 7.
Connections must also be configured (using NetPro) for the use of S7 communication. For

this purpose, connection resources have to be available, which are not allocated to PG/OP

or other connections. The required S7 connections are then permanently allocated for

S7 communication when the configuration is uploaded to the CPU.