Initial Startup Checks and Commissioning Procedure for Warranty Inspection

108

11.0 I

NITIAL

S

TARTUP

C

HECKS

AND

C

OMMISSIONING

P

ROCEDURE

FOR

W

ARRANTY

I

NSPECTION

• Confirm that all items on 10.0 - Checklist for Completed Installation have been done.
• Locate “Liebert DS Warranty Inspection Check Sheet” in unit electric panel. (Document number

SAFM-8542-29)

• Complete “Liebert DS Warranty Inspection Check Sheet” during startup. (Document number

SAFM-8542-29) This information must be completed and forwarded to Emerson to vali-

date warranty.

• Forward the completed “Liebert DS Warranty Inspection Check Sheet” to your local Emerson

sales office.

• Contact your local Emerson sales representative or Liebert Air Product Support if you have any

questions or problems during unit startup and commissioning.

• Local Emerson Sales offices and Liebert Air Product Support contacts can be found at

www.liebert.com

or by calling 1-800-LIEBERT.

Liebert DS Warranty startup procedure includes the following steps. These steps must be completed

to validate warranty.

!

WARNING

Risk of electric shock. Can cause injury or death
Disconnect local and remote power supplies before working within.
Before proceeding with installation, read all instructions, verify that all the parts are included

and check the nameplate to be sure the voltage matches available utility power.
Follow all local codes.

!

WARNING

Risk of improper wiring, piping, moving, lifting and/or handling. Can cause equipment

damage, injury or death.
Only qualified service personnel should move, install or service this equipment.
Read all installation, operating and safety instructions before proceeding.
Read and follow all warnings on page 1 and elsewhere in this manual.

!

WARNING

Risk of fire suppression and alarm system activation. Can cause injury during building

evacuation and mobilization of emergency fire and rescue services.
Startup operation of optional electric reheat elements may activate facility alarm and fire

suppression system. Prepare and take appropriate steps to manage this possibility. Activating

reheat during initial startup may burn-off particulate from electric reheat elements.
Before beginning initial startup checks, make certain that unit was installed according to the

instructions in this manual. All exterior panels must be in place.