5.3 Maintenance and cleaning activities

(general steps)

5.3.1 General information

Maintenance activities have to be done at regular intervals on the
P 700 IQ.

The preparation of the P 700 IQ depends on whether the maintenance
activity should be done while the P 700 IQ is closed or open.

Tab. 5-3: Maintenance activities

Maintenance
activity

P 700 IQ

Interval

Purge manually

Closed

As required
(see section 5.3.3,  71)

Calibrate manually

Cleaning the filter
membrane

2 ... 4 weeks
depending on application
(see section 5.4.5,  88)

Changing the filter
membrane

If cleaning does not achieve
any improvement
(see section 5.4.6,  92)

Changing the liquid
containers

Open

(Overall:
section
5.3.4,  73)

Approx. 4 months
depending on the frequency of
measurement, cleaning, cali-
bration
(see section 5.4.1,  76)

Changing the valve
tubes (T SET)

12 months
(see section 5.4.3,  79)

Changing the filter
mats

Depending on contamination
(see section 5.4.2,  78)

Changing the
pump tube of the
peristaltic pump

12 - months
depending on measuring
interval
(see section 5.4.4,  83)

Cleaning the over-
flow vessel

12 months (recommended)
section 5.4.7,  93

Perform a
Hydraulic check

When necessary
section 5.4.8,  94