Before you begin the maintenance tests – ZOLL Propaq MD Rev A User Manual

Page 10

Advertising
background image

C

HAPTER

1

M

AINTENANCE

T

ESTS

6

9650-0807-01 Rev. A

This chapter describes the following maintenance tests:

Physical Inspection of the Unit

Operational Tests

Leads Test

Heart Rate Display Test

Heart Rate Alarm Test

Leakage Current Test

Shock Test

Advisory Test

Synchronized Cardioversion Test

Pacer Test

Printer Test

Treatment Report Test

SpO

2

Monitor Test

EtCO

2

Calibration

EtCO

2

Calibration Check

EtCO

2

Monitor Test

IBP Monitor Test

NIBP Calibration Test

NIBP Leak Test

Deflation Test

Inflation Test

NIBP Monitor Test

Temperature Test

Before You Begin the Maintenance Tests

Assemble the tools listed in following section, “Equipment You Need to Perform the

Maintenance Tests.”

Keep an extra fully charged Propaq MD battery available.

Schedule an hour to conduct the entire maintenance test.

Perform the tests in the order presented.

Perform all the steps of each test procedure.

Complete all the steps of the procedure before evaluating the test results.