3 installation guide and schematic – INFICON XTM/2 Thin Film Deposition Monitor User Manual

Page 33

Advertising
background image

2 - 7

IP

N 07

4-

18

6S

XTM/2 Operating Manual

2.3 Installation Guide and Schematic

Many experienced deposition monitor users will be able to fully install and use
the instrument by studying the installation schematic,

Figure 2-5

on the next

page, and the State Sequence Diagram,

Figure 4-2 on page 4-2

.

A more systematic approach would be to start by reviewing the two figures and
then following the procedure below.

WARNING

Completely review

section 1.1 on page 1-1

on safety.

All warnings in this section, as well as ones found in
other sections listed below, must be followed to ensure
the safety of the personnel operating this equipment.

1

Check for correct line voltage,

section 2.2 on page 2-3

.

2

Verify basic unit operation by exercising it in the Test Mode,

section 3.6 on

page 3-11

.

3

Review the system interface capability as outlined in

section 2.5 on page

2-13

. Be especially attentive of the special features available on the

configuration switches,

section 2.5.2 on page 2-15

4

Wire the necessary connectors following the installation procedures in

section 3.1 on page 3-1

,

section 3.2 on page 3-1

, and

section 3.3 on page

3-4

.

5

Review the front panel controls and display description per

section 2.4 on

page 2-9

.

6

Program the desired film parameter values per

section 4.1 on page 4-1

and

section 4.2 on page 4-3

.

7

Verify the operation of the just programmed film utilizing the Test Mode.

8

Attach the XIU (757-305-G15, G30, or G100) to an existing transducer or
install a new transducer following the guidelines of

section 3.5 on page 3-7

and

Figure 3-3 on page 3-8

.

9

Exit the Test Mode and deposit when ready.