Please do not change the switch-on sequence explained below!

Stop!

Prior to first switch-on of the controller, check the wiring for

Completeness

Short circuit

Earth fault

Step

Procedure

Remarks

1.

Connect the basic unit and
if available external supply for the fieldbus
module.

Onle of the two operating status LEDs at the controller, see

^ 4-1, must be on

or blinking.

If this is not the case, see

^ 7-1

The green Vcc display must also be on, see

^ 4-1.

If this is not the case, see

^ 7-1.

2.

Configuration of controllers connected to
the bus

Configure the controllers connected to the bus by means of an appropriate
configuration tool

à

e.g. LONMAKERtfor Windows

®

, see

^ 8-1

3.

It should now be possible to communicate
with the drive.

The yellow bus LED is blinking, see

^ 4-1, when data is exchanged between

the 2141 fieldbus module and other controllers connected to the bus.

4.

Drive-specific settings

à

Operating Instructions of the basic unit

5.

Enable controller

à

Terminal controller inhibit (CINH) = HIGH

6.

Setpoint selection

à

The drive should be running now.