Commissioning the Drive Chapter 4

Bypass Contactor Closures

Sample Waveforms

Ch1: Bypass Contactor Close Command (BPC output at ACB, J1-12 & 402)

Ch2: Actual Closure of Bypass Contactor (using 9V battery across contactor
vacuum bottles)

Figure 87 - Sample waveform: Bypass contactor closures

Synchronous Transfer Test: Verify Sync Lead Angle

While simulating a synchronous transfer to determine the best lead angle:

ensure you have configured and armed the Diagnostic Trend.
capture motor voltage at ACB test point “Vuv” & bypass voltage at ACB

test point “Vuvs”.

capture and trigger on falling edge of the DC Link current waveform at

ACB test point “Idc1”.

label the waveforms as “Vuv”, “Vuvs” and “Idc1”.
save the worksheet as “Drift @ 15 Degree Lead Angle”, for example.

Table 9 - Oscilloscope Settings

Oscilloscope

Time Base

Wave Form

Test-Point

Waveform
Label

Chan. 1

10ms/div.

DC Link Current

Idc1

Idc1

Chan. 2

Motor Voltage

Vuv

Vuv

Chan. 3

Bypass Line
Voltage

Vuvs

Vuvs