Commissioning Preparations Chapter 3

Pre-Commissioning Responsibilities

The customer must complete the pre-commissioning checklist; refer to the
Publication

7000-IN007_-EN-P

for the customer’s full pre-commissioning

checklist, as well as sign-off dates and signatures indicating completion of the
required tasks.

Commissioning Preparation

The following section identifies all the tools and resources required to
successfully commission a PowerFlex 7000 ‘B’ Frame drive. In addition, it
identifies how to obtain the required equipment in the event that it is not readily
available prior to commissioning the drive. It is recommended that all items listed
below be obtained prior to attempting to commission the drive. The contents of
this section must be reviewed and that the uses of the equipment described
within are understood prior to commissioning of the drive. If support or
additional information is required, contact your local Rockwell Automation
service office or Medium Voltage Support at (519) 740-4790.

Recommended Tools and Equipment

Hand Tools

Metric and Imperial wrenches, sockets, and Hex keys

Torque wrench

Assortment of screw drivers

Assortment of electrical tools (wire strippers, electrical tape, crimpers, etc.)

Electrical Equipment

High voltage gloves – 10 kV insulation rating (minimum)

Approved high voltage potential tester – 10 kV rating (minimum)

Anti-static strap

Test Equipment

100 MHz or higher oscilloscope with at least two channels and memory

600V (1000V rating) digital multimeter with assorted clip leads

Megohmmeter with selectable voltage 2500/5000V