Drive Main Circuit Test Procedure

Before attempting any troubleshooting checks, make sure that the three-phase power is disconnected and locked out. With power removed
from the unit, the DC bus capacitors will stay charged for several minutes. The Charge LED in the Drive will glow red until the DC bus volt-
age is below 10Vdc. To ensure that the DC bus is completely discharged, measure between the positive and negative bus with a DC voltme-
ter set to the highest scale.

WARNING

Prior to removing any protective cover or wiring any part of the Drive, remove all power sources, including

main input power and control circuit power. Wait a minimum of 5 minutes after power removal, before

removing any cover. The charge lamp located within the Drive should be off prior to working inside. Even if

the charge lamp is off, one must measure the AC input, output, and DC Bus potential to insure safe levels

prior to resuming work. Failure to adhere to this warning may result in personal injury or death.

Table 6.6 Main Circuit Test Procedure

Check

Procedure

Measure DC Bus Voltage

1. Set the digital multi-meter to its highest VDC scale.
2. Measure between

⊕ 1 and (-) for the following check:

Place the positive (red) meter lead on

⊕ 1.

Place the negative (black) meter lead on (-).

3. If the measured voltage is < 10Vdc, it is safe to work inside the Drive.

If not, wait until the DC Bus has completely discharged.

Input Diodes

(D1-D12 or Q1)

The input diodes rectify or transform the three-phase input AC voltage
into a DC voltage.
1. Set a digital multi-meter to the Diode Check setting.
2. Place the positive (red) meter lead on terminal R/L1.

Place the negative (black) meter lead on terminal

⊕ 1.

Expected reading is about 0.5 Volts.

3. Place the positive (red) meter lead on terminal S/L2.

Place the negative (black) meter lead on terminal

⊕ 1.

Expected reading is about 0.5 Volts.

4. Place the positive (red) meter lead on terminal T/L3.

Place the negative (black) meter lead on terminal

⊕ 1.

Expected reading is about 0.5 Volts.

5. Place the positive (red) meter lead on terminal R/L1.

Place the negative (black) meter lead on terminal (-).

Expected reading is OL displayed.

6. Place the positive (red) meter lead on terminal S/L2.

Place the negative (black) meter lead on terminal (-).

Expected reading is OL displayed.

7. Place the positive (red) meter lead on terminal T/L3.

Place the negative (black) meter lead on terminal (-).

Expected reading is OL displayed.

8. Place the positive (red) meter lead on terminal (-).

Place the negative (black) meter lead on terminal R/L1.

Expected reading is about 0.5 Volts.

9. Place the positive (red) meter lead on terminal (-).

Place the negative (black) meter lead on terminal S/L2.

Expected reading is about 0.5 Volts.

10. Place the positive (red) meter lead on terminal (-).

Place the negative (black) meter lead on terminal T/L3.

Expected reading is about 0.5 Volts.