GE Industrial Solutions GE Zenith Series DPB User Manual

Page 22

Advertising
background image

14

Installation & Operation Manual, GE Series DPB Busway
March 25, 2013, Rev 0

GE Confidential

Series DPB Busway Installation & Operation Manual

12.) Position the Dowel Pin into the round port between the first pair (viewed left-to-right, or right-to-left) of

installed white-tipped, slotted Cam Spacers. The conical pointed end is inserted first, and the end with
the O-ring inserted last. (See Figure 8.3)

13.) Using pressure push the Dowel Pin so that it is inserted completely into the Cam Actuator Tool Hole.

(See Figure 8.4)

14.) Make sure that the O-ring on the dowel is inside the E-clip. (See Figure 8.5)



15.) Repeat Step 13 until all four (4) vacant Cam-Actuator Tool Ports have Dowel Pins in them.

16.) Repeat the process for each splice in the bus run until complete.

Figure 8.3 - Positioning of Dowel Pins

Figure 8.4 - Insertion of Dowel Pin

Figure 8.5 - Dowel Pin O-Ring Inside "E" Clip

E Clip

E Clip

Before

After

Before

After