Series dpb busway installation & operation manual – GE Industrial Solutions GE Zenith Series DPB User Manual

Page 26

Advertising
background image

18

Installation & Operation Manual, GE Series DPB Busway
March 25, 2013, Rev 0

GE Confidential

Series DPB Busway Installation & Operation Manual

vii) Rotate and remove the cam actuator tool in cam port #4, and insert it into cam port #6. Rotate the

steel tool in cam port #6 to expand the contact plates.

viii) Rotate the adjacent, non-metallic cam spacers (g & h), ¼ turn.

ix) Rotate and remove the cam actuator tools.

8.) CAUTION: DO NOT proceed to 9) Installation of the Dowel Pin Devices until the Cam Spacers are

verified to be in the locked position. A properly installed Splice, when viewed from the bottom (open
channel) of the joined bus sections will show the Cam Spacers in the Locked Position as show in Figure
15.1 below.

9.) Installation Of The Dowel Pin Devices


The Dowel Pins are used to secure open Cam Actuator Tool ports and add Cam Spacer functionality.
Material Required for Initial Installation (before busway is energized*):

Six Dowel Pin Devices

10) Inspect the busway, and verify that the splice connections of the busway have been installed correctly

per INSTALLATION OF THE SPLICE CONNECTOR – 400 AMP.

1. Verify no gaps between the bus connections

2. Verify the E-clips are positioned properly.

3. Verify the Cam Spacers (white-tipped, slotted lock pins) are positioned properly.

* please contact factory service for dowel pin installation procedure when working on an energized

busway (800-225-4838)

a

Cam

Port #1

Cam Spacers

bottom view

Cam

Port #2

b

c

d

e

f

g

h

Cam

Port #3

Cam

Port #4

Cam

Port #5

Cam

Port #6

a

Cam

Port #1

Cam Spacers

Cam

Port #2

b

c

d

e

f

g

h

Cam

Port #3

Cam

Port #4

Cam

Port #5

Cam

Port #6

1

2

3

4

5

6

1

2

3

4

5

6

a

Cam

Port #1

Cam Spacers

bottom view

Cam

Port #2

b

c

d

e

f

g

h

Cam

Port #3

Cam

Port #4

Cam

Port #5

Cam

Port #6

a

Cam

Port #1

Cam Spacers

Cam

Port #2

b

c

d

e

f

g

h

Cam

Port #3

Cam

Port #4

Cam

Port #5

Cam

Port #6

1

2

3

4

5

6

1

2

3

4

5

6

bottom view

cam spacer alignment before installation

cam spacer position - splice installation complete as seen from bottom

Figure 15 - Splice Installation Detail 400 Amp

Cam Spacer

Cam Actuator Tool Hole

Cams in Locked Position

Figure 15.1 - Cam Spacers in Locked Position