Installation & Operation Manual, GE Series DPB Busway
March 25, 2013, Rev 0

GE Confidential

Series DPB Busway Installation & Operation Manual

2.) Slide the C-clip into bus rail positioning the C-clip as shown in (Figure 11 - Busrail C-Clip Profile View - 400 Amp).

NOTE: Do

not tighten the screws yet.

3.) Position a Splice Connector into the bus rail that has been properly mounted and supported (leveled, aligned).

NOTE: When the busway is mounted horizontally, make sure the Cam Spacers are flush with the top of the Splice Connector
before positioning the assembly. (See Figure 12 - Cam Spacers)

4.) Bring the ends of busrails to be spliced together, position the Splice Pack equally across the joint, position the E-clips, Side
Support Plates, and Grounding plate ready for Splice cam actuation. (See Figure 13 - Busrail C-Clip Splice and E-Clip Loca-
tion - 400 Amp).

5.) Install the Splice per section "INSTALLATION OF THE SPLICE CONNECTOR - 400 AMP".

6.) Position and tighten the two screws of each C-clip.

Figure 11 - Busrail C-Clip Profile View - 400 Amp

Figure 13 - Busrail C-Clip Splice and E-Clip Location - 400 Amp

C-clip

E-clip

Figure 12 - Busrail Cam Spacers

Cam Spacer