3 system planning, System planning -2, Overview of the planning steps – YSI IQ SensorNet 2020 XT Terminal User Manual

Page 32

Advertising
background image

Installation

System 2020 XT USB

3 - 2

ba76019e01

12/2012

3.3

System planning

Overview of the

planning steps

Fig. 3-1

System planning

- Sum of all line lengths max. 1000 m
- Of these, max. 500 m branch lines

altogether

- Single branch line max. 250 m

Total line lengths of > 1000 m
can be realized with the
signal amplifier module

MIQ/JBR

Total line lengths < 400 m
not have to be taken into account

do

More power required due to cable losses:
From

1 watt per

100 m additional line length.

400 m total line length

- Position power supply modules near

main consumers (e. g. UV/VIS sensor)

- Further power supply module or adjust-

ment of infrastructure if necessary.

Power requirement =

SP of all consumers

- Number and types of required sensors
- Measuring locations to be designed
- Number of required operating locations
- Distances
- Infrastructure, process environment etc.

Rough planning

Rough determination of power requirement

Consideration of cable losses

Rating

Fine adjustment

IQ

topology + layout

S

ENSOR

N

ET

Power requirement of components

Total power requirement

Number of power supply modules

required

Fundamentals of planning

Start

End

SP of all power supply modules >
total power requirement

Arrangement of

power supply modules

Advertising