Preparing the cable

ends

Fig. 3-14 Prepared cable end

Connecting the cables

The SNCIQ and SNCIQ/UG cables are connected to the terminal strip
in the same way as the SACIQ sensor connection cable (see section
3.5.4
):

1

Cut off the cable to the required length.

2

Remove approx. 45 mm of cable insulation (in the case of the
SNCIQ/UG earth cable, remove both the inner and outer
insulation).

3

Only for the SNCIQ/UG earth cable:
strip the outer insulation for further 35 mm.

4

Shorten the exposed shielding braid up to the cable sheath.

5

Shorten the two fillers (plastic inlays) up to the cable sheath.

6

Bare the red and green wires and fit them with wire end
sleeves.

7

Fit the filler stranded wire with a wire end sleeve.

SNCIQ

SNCIQ/UG

approx. 35 mm

approx. 45 mm

approx. 45 mm

1

Open the MIQ module.

2

Select any SENSORNET connection. At the same time, look
out for the SENSORNET designation.