YSI IQ SensorNet 2020 XT Terminal User Manual
Page 73

System 2020 XT USB
Installation
3 - 43
ba76019e01
12/2012
Configuration of the
MIQ/TC 2020 XT
During the commissioning of the MIQ/TC 2020 XT at the
IQ S
ENSOR
N
ET
a query appears asking whether the MIQ/TC 2020 XT
should work as a controller or just as a terminal. Select the required
function for each MIQ/TC 2020 XT.
Fig. 3-29 Selecting the instrument type
The MIQ/TC 2020 XT will then try to register with the selected
functionality on the IQ S
ENSOR
N
ET
. Note that only one controller can
be active in an IQ S
ENSOR
N
ET
.
Details on the configuration of the MIQ/TC 2020 XT, see section 3.11.
Initial start phase
In the initial start phase, all IQ S
ENSOR
N
ET
components are
automatically registered on the MIQ/TC 2020 XT controller module and
the terminal is initialized. Then, the system performs a self test. This
process may last a few seconds. During this period, the following
display appears:
Fig. 3-30 Display during the initialization process