4. Commissioning

4−39

Festo P.BE−CPX−CMA X−SYS−EN en 0908NH

Operating voltage = 0 V
Load voltage (valve) = 0 V

CMAX is OFF

SCON.MC = 0

SCON.24VL = 0

The output data should be filled at the beginning in
any case so that no control signals from the last
operating phase can affect the CMAX.

Error:

CMAX does not signal

Reset PLC output

data

Switching on the

operating voltage

Start timer:

3 seconds

The CMAX initialises the axis string and the controller
and queries the setting for the data format in the CPX
node.

Monitoring to discover a defective module. Time can
vary, depending on the CPXC node.

[m]

[m]

[m]

[m]

[o]

[o]

Timer expired

Time is still

running

SCON.FAULT = 0

SCON.FAULT =
1

SCON.MC = 1

Check commissioning

status

Cancel

Error handling

Switch on pressure

Setting the operating

mode

Switch on valve load

voltage (= 24 V)

SCON.FAULT = 0

SCON.FAULT = 1

SCON.24VL = 1

Page

2

Cancel

Error handling

[m]

[m]

[m]

[m]

[m]

[o]

The operating pressure should be completely on the valve within 50 ms.
Otherwise, plan an additional waiting time after this step or parameterise E50
as a warning.

It is imperative that this action
be executed.

This action is a recommendation.
It does not have to be executed.

[m]

[o]