4. Commissioning

4−12

Festo P.BE−CPX−CMA X−SYS−EN en 0908NH

4.3

Commissioning with the FCT (overview)

Detailed information about commissioning with the FCT can
be found in the Help for the FCT CMAX plug−in.

Information for specialists concerning commissioning via the
CPX node can be found in the CMAX communication profile"
description.

4.3.1

Overview of commissioning steps

The following steps are typically carried out during commisĆ
sioning:

1. If necessary, check the structure of the positioning

system with the components used on the axis string
(see section 4.2.1).

2. Check the power supply of the CPX terminal and switch on

the power supply (see section 4.2.2).

Caution: Leave the compressed air supply switched off for
the moment.

3. Create or open a project in the FCT. Add a new component

with the CMAX plug−in.

4. Establish a connection (online) between the PC and CMAX

via the FCT toolbar.

5. When CMAX is in its delivery status (display: C00), the

configuration wizard is started automatically when the
device connection is being established.

The CMAX can be configured with and without connected
components (in the office"). If the valve and sensor interĆ
face have been connected, the CMAX automatically deĆ
tects the hardware after being switched on. The data deĆ
tected here is accepted by the FCT. If commissioning is
done without components, all data must be entered.