Page 86: Checking the axis string, Switching on the power supply, switch−on behaviour

Advertising
background image

4. Commissioning

4−8

Festo P.BE−CPX−CMA X−SYS−EN en 0908NH

4.2

Preparations for commissioning

4.2.1

Checking the axis string

Prior to commissioning:

·

Check the complete system structure, especially the drive
tubing connections and the electrical installation (see
chapters 2 and 3).

It is possible to pre−parameterize the CMAX even without the
components on the axis interface.

4.2.2

Switching on the power supply, switch−on behaviour

Warning
High acceleration forces on the connected actuators! UnexĆ
pected motions can cause collisions and severe injuries.

·

Switching on:
Always first switch on the valve load voltage supply and
then the compressed air supply.

·

Switching off:
Before mounting, installation and maintenance work, put
the system into a safe state (e.g. by putting the drive in a
safe position and deactivating the controller).
Always make sure that the compressed air and valve load
voltage supplies are switched off and locked before
working in the machine area.