Preventative Maintenance Schedule

Time Estimations

Tool / Parts / Information Requirements

The following is a list of the tools recommended for proper maintenance of the
PowerFlex 7000 drives. Not all of the tools may be required for a specific drive
preventive procedure, but if we were to complete all of the tasks listed above the
following tools would be required.

Tools

100 MHz Oscilloscope with minimum 2 Channels and memory

5 kV DC Megger

Digital Multimeter

Torque Wrench

Laptop Computer with Relevant Software and Cables

Operational Maintenance

0.5 hours per filter

Annual Maintenance

Initial Information Gathering

0.5 hours

Physical Checks

Torque Checks

2.0 hours

Inspection

2.0 hours

Cleaning

(1)

(1) Time may not be required depending on the nature of the maintenance and the condition of the drive system. These times are only

estimations.

2.5 hours

(1)

Meggering

1.5 hours

Control Power Checks

Contactor Adjustments

(1)

2.0 hours

(1)

Voltage Level Checks

1.0 hour

Firing Check

0.5 hours

System Test

(1)

2.0 hours

(1)

Medium Voltage Checks

Final Inspection

0.5 hours

Phasing Check

(1)

1.5 hours

(1)

Autotuning

(1)

2.0 hours

(1)

Operation to Maximum Load

Site Dependent

Additional Tasks

(1)

Investigation

Varies with nature of Problem

Informal Training/Refresher

2.0 hours

Spare Parts Analysis

1.0 hour

Vacuum Bottle Integrity Check

3.0 hours

Final Report

3.0 hours