Metering

44

4

NOTE: When a meter is removed from a circuit breaker, all data accumulated at that circuit
breaker (e.g., maximum demands, demand log information, and energy values) are cleared.

Because all metering information available with the expanded metering option is also available
with the demand metering option, and all metering information available with the demand
metering option is also available with the advanced metering option, it does not make any
sense to enable more than one meter type for a given circuit breaker. The HMI prevents the
enabling of more than one meter type for a given circuit breaker. The HMI also prevents the
enabling of more meters than the number of metering options purchased.

Figure 4-3 Configuring demand calculations