36 - 8630

F

IRST

C

OMMISSIONING

After application of the supply voltage, the TOP Control

Continuous is in operation. Carry out the

necessary basic settings and initiate self-parametrization of the TOP Control.

NOTE

Further installation notes are to be found in the chapter

Installation.

➔ Remove the cover with the cable bushings

to gain access to the terminals. This is done
by unscrewing the 4 self-tapping screws.

➔ Apply the setpoint signal and the supply

voltage to the respective terminals (see
Terminal configuration with cable bushings).

Terminal

Allocation

External connection

1

Setpoint +

2

Setpoint GND

5

Operating voltage +

6

Operating voltage GND

24 V DC ± 10 %
max. residual ripple 10 %

2

1

+ + (0/4 ... 20 mA or 0 ... 5/10 V)

GND

5

6

Terminal configuration with cable bushings

* Electrical installation - connection terminals for cable bushings