1 Connect the grounding wire from either the DIN rail or a GND screw terminal on the UN-

PROTECTED side of the Click 200 to the lug bolt on the inside of the pole-mount cabinet.

2 Connect another grounding wire from the exterior lug bolt to earth ground (see Figure 2.4).

Figure 2.4 – Earth Ground Connections

Installing the Power Plant

Provide power to your installation using the Click power plant. This set of modules includes

the following:

˽

Click 201/202 AC to DC converter

˽

Click 210 circuit breaker and switch

˽

Click 230 AC surge module

A Click 201 provides 1 A of power and is capable of powering a single sensor, while a Click

202 provides 2 A and can power two sensors. (There is also a Click 204 which provides 4 A

of power, but that will usually not be necessary in an installation such as the one outlined

below.) The Click 230 helps limit current surges on the power lines; the Click 210 interrupts

power during overload conditions and provides a convenient way to turn power on and off.

The power plant will either be in a pole-mount box or in a main traffic cabinet. If it’s in a

traffic cabinet, the power will be sent to the pole via an underground cable run. How to in-

stall the power plant and then wire to a Click 200 will be covered in the rest of this section.

It should be noted that if you have ordered a Wavetronix preassembled cabinet, all of this

wiring and installation will already be done.