General Requirements

Before assembling or installing the switchgear equipment, all

components should be available at the site location. This will

facilitate switchgear component identification as well as

installation. The foundation should be prepared in

accordance with the instructions in Sections 4-1 and 4-2, and

all embedded conduits installed and capped.

NOTE: If rollers are to be used for movement of the

equipment to its permanent installation, it is

recommended that the shipping skid not be removed until

the equipment is placed in position over the anchor bolts.

NOTE: Au cas où l’utilisation de rouleaux s’avérerait

nécessaire afin d’apporter l’équipement à son

emplacement permanent, nous recommandons que

l’emballage d’expédition ne soit pas enlevé tant que

l’équipement n’est pas positionné au dessus des boulons

d’ancrage.

If a transformer is not part of the installation, and/or the

equipment has been split for shipment, place the center

section on the foundation first. Assemble the remaining

sections outward from the center section, in each direction.

If the switchgear equipment is part of a Load Center Unit

Substation, the transformer section should be set on its pad

first in accordance with the instructions furnished with the

transformer. All remaining sections of the switchgear should

then be installed.

NOTE: Before assembling and installing the switchgear

equipment, the foundation must be absolutely level and

clear of debris to prevent damage and possible

misoperation of the switchgear equipment.

NOTE: Il faut avant de procéder à l’assemblage et à

l’installation s’assurer que la fondation soit absolument

au niveau et exempte de débris afin de prévenir des

dommages à l’équipement du dispositif de commutation.


Detailed Assembly and Installation
Instructions

The recommended procedure for installation of a switchgear

or Load Center Unit Substation is as follows:

1.

POSITION THE EQUIPMENT-Position the equipment

or sections of the complete equipment in their final

location.

Fig. 4-4. Lifting plate location

NOTE: If the equipment line-up was split into shipping

sections, the lifting plates on corners of adjacent sections

shown in Fig. 4-4 must be removed. Failure to remove

these plates will interfere with mating adjacent sections

and prevent installation of bus splice plates, structure tie

plates, etc.

NOTE: Si l’ensemble de l’équipement a été séparé en

sections pour l’expédition, il faut que les plaques de

soulèvement aux coins des sections adjacentes montrées à

la Fig. 4–4 soient enlevées. L’omission d’enlever ces

plaques viendra en interférence avec les sections barres

omnibus, de l’attache de la structure des plaques, etc.

Once the lifting plates have been removed, they may be

discarded.

NOTE: In the event the lifting plates must be

reassembled on the equipment for lifting purposes, they

must be moved to locations where unused screw holes are

avail-able, generally achieved by shifting the plate

horizontally on the mounting surface one bolt hole from its

previous location. When remounting the lifting plates,

torque the mounting bolts to 7-9 ft-lbs.

NOTE: Dans l’éventualité où les plaques de levage doivent

être réassemblées sur l’équipement à des fins de levage,

elles doivent être déménagées aux endroits où il y a des

trous de boulons inutilisés, on y arrive habituellement en

décalant la plaque horizontalement sur la surface de

montage d’un trou de boulon de son emplacement

précédent. Lors du remontage des plaques de levage,

serrer les boulons d’assemblage à un couple de 7–9 livres-

pied.