Entellisys Low Voltage Switchgear

Chapter 8. Energizing the Switchgear

8-1 Before Energizing

Before switchgear is energized, a thorough final check should

be made using the following checklist: Refer to section 6-5 for

additional information.

• Breakers and other operating mechanisms exercised

• Electrical insulation resistance tested phase-to- phase

and phase-to-ground

• Entellisys instrumentation properly connected

• Electrically operated breakers and operating mechanisms

tested

• Ground fault protection system tested

• Protection settings properly set and tested.

• Field wiring secured and free of live bus

• Grounding connections made

• All debris, scrap wire, etc. removed

• All covers installed, doors closed and latched

8-2 Energizing Procedures

CAUTION: Energizing switchgear for the first time is

potentially dangerous. Therefore, qualified electrical

personnel should be present when the equipment is

energized. If problems caused by damage or poor

installation practices have not been detected in the

checkout procedure described previously, serious damage

can result when power is turned on.

ATTENTION: La mise sous tension pour la première fois

d’un dispositif de commutation est un acte potentiellement

dangereux. Il faut donc que du personnel qualifié en

électricité soit présent lorsque l’équipement est mis sous

tension. Si lors de la procédure de vérification décrite

précédemment des problèmes causés par des dommages ou

de mauvaises pratiques d’installation n’ont pas été

détectés, il peut en résulter des dommages sérieux lorsque

le contact est établi.


1.

There should be no load on the switchgear when it is

energized.


2.

Turn off all of the downstream loads, including those

such as motor control centers and other devices that

are remote from the switchgear.


3.

The equipment should be energized in sequence by

starting at the source end of the system and working

toward the load end. In other words, energize the main

devices, then the feeder devices, and then the branch-

circuit devices.

4.

Turn the devices on using the Entellisys HMI.