38

Entellisys Low Voltage Switchgear

Chapter 4. Equipment Installation

The hoist should be lifted into position on top of the

switchgear so that the end with two rollers is toward the rear

of the equipment, Fig. 4-21.

Fig. 4-21. Location of hoist rear rollers


The rear wheels can then be hooked under the channel and

the front wheels can be positioned on the front track. See

Fig. 4-22. The runner guide at the rear should then be

reassembled, Fig. 4-23. Stop clips are provided at each end of

the front track to prevent the hoist from rolling off the ends of

the track.

Fig. 4-22. Front rollers positioned on front track

Fig. 4-23. Replacing the runner guide after completion of hoist

installation

Fig. 4-24. Removing the bracket locking the hoist dolly

If the equipment has been shipped in sections, run the hoist

carriage over the assembled shipping split to check the

alignment of the hoist rail and runner. If necessary, adjust

the rail and/or runner for smooth operation of the rollers on

the hoist carriage.

On seismic rated equipment, it is necessary to remove the

bracket locking the hoist dolly on the carriage before the

hoist can be used, Fig. 4-24. Replace the bracket after

breaker installation or removal is complete.

Final Inspection

Make a final inspection to see that no tools, construction

materials, or other foreign matter have been left in the

switchgear equipment.