Entellisys Low-voltage Switchgear

Chapter 6. Testing and Inspection

6-5 Final Steps to Be Taken Before

Energizing Equipment

The following steps should be taken before energizing the

equipment:

1.

Manually exercise all switches, circuit breakers, and
other operating mechanisms to make certain they are

properly aligned and operate freely.


2.

Conduct an electrical insulation resistance test to make

sure the switchgear is free from short circuits and
grounds. This should be done both phase-to-ground and

phase-to-phase with the switches or circuit breakers

both opened and closed. This test should be performed

with a 1000-volt megger. Disconnect all control circuits

before checking resistance.

3.

Check for secure mounting and wiring connections at
Entellisys instrumentation.

4.

Using the Entellisys HMI, exercise all EntelliGuard

breakers to determine all devices work correctly. See

DEH-231 for instructions on using the Entellisys HMI.

.
5.

Test all protection functions using the Entellisys
System Test Kit. See DEH-233 for instructions.


6.

Make certain that field wiring is clear of live bus and,

where necessary, physically secured to withstand the

effects of fault currents.

7.

Check to determine that all grounding connections are

made properly.

8.

Remove all debris, scrap wire, etc., from the switchgear

interior before closing the enclosure.

9.

Install covers, close doors, and make certain that no

wires are pinched and that all enclosure parts are

properly aligned and tightened.