Entellisys Low-voltage Switchgear

Chapter 6. Testing and Inspection

6-1 General

After the equipment has been installed and all connections

made, it must be tested and inspected before it is put in
service. Although the equipment and devices have been

tested at the factory, a final field test must be made to be sure

that the equipment has been properly installed and that all

connections are correct.

WARNING: The equipment must be completely de-

energized while the tests are in progress.

ADVERTISSEMENT:

L’équipement doit être

complètement désamorcé lorsque l’on procède à des tests.

Directions for testing Entellisys instrumentation is provided

in DEH-231 (Entellisys System User’s Manual) and DEH-233
(Entellisys System Test Kit User’s Manual.) The proper

settings of Entellisys instrumentation are normally

determined from a complete power system coordination study

performed by the purchaser or their consultant; therefore, the

settings of these devices must be made by the purchaser.

NOTE: The trip setting adjustment of the EntelliGuard

Messenger for each circuit breaker may be in any position

when shipped from the factory and must be correctly

positioned prior to energization of the equipment.

NOTE: Les ajustements des réglages du disjoncteur

peuvent être en n’importe quelle position lorsque celui-ci

est expédié de l’usine et ils doivent être positionnés

correctement avant que l’équipement ne soit mis sous

tension.

The extent of the tests on the equipment as a whole will

depend on the type and function of the equipment. Tests that

should be performed, however, include circuit breaker

operation, and switchgear meggering, phasing, and grounding

checks.

High-potential tests to check the integrity of the insulation
are not necessary if the installation instructions are carefully

followed. If local codes demand this test, or the purchaser

wishes to make high-potential tests, the voltage should not

exceed 75 percent of the IEEE factory test voltage.

For the power circuit, the IEEE factory test voltage is two

times switchgear rating plus 1,000 volts. See Table 6-1.
Potential and control power transformers must be

disconnected during high-voltage testing.

Switchgear

Voltage Rating

ANSI

Test Voltage,

AC RMS

Field

Test Voltage,

AC RMS

600V

480V
240V

2200V

1960V
1480V

1650V

1470V
1110V

Table 6-1

6-2 Key Interlocks

After initial installation of the switchgear equipment, all

necessary interlock keys should be inserted into the
appropriate locks and all spare keys should be stored in a

location in accordance with the owner's established

procedures.

CAUTION: Refer to the key interlock schematic included

in the summary furnished with the equipment to deter-

mine the sequence of operation and the correct number of

operating keys required. This precaution is necessary

since the improper use of spare keys will defeat the

interlocking scheme.

ATTENTION: Référez-vous au schéma des clés de

verrouillage inclus au sommaire fourni avec l’équipement
pour déterminer les séquences d’opération et le nombre

correct de clés d’opération requises. Cette précaution est

nécessaire étant donné qu’un mauvais usage des clés de

réserve rendra inopérant le programme de verrouillage.

6-3 Breaker Operation Test

All compartments housing EntelliGuard circuit breakers have
a TEST position in which the breaker primary contacts are

disconnected while the secondary contacts are still engaged.

This TEST position permits complete testing of the electrical

control circuit without energizing the primary power circuit.

When the breaker is first put into service, its control circuit

must be thoroughly tested while in this position to make sure
that all closing and tripping circuits are complete and

functioning properly.

The TEST position is not suitable for inspection and

maintenance of the breaker and should therefore be used only

for testing breaker operation.

Refer to the appropriate breaker instruction manual for other

pre-operational checks on the breakers. See DEH-201 or

DEH-202.

6-4 Entellisys System Test Kit

An Entellisys System Test Kit is required for testing

Entellisys Low Voltage Switchgear functionality. The system

test kit user manual is DEH-233.